Advertisement for Bids - City of Lake City - Electric Distribution System
ADVERTISEMENT FOR BIDS
Sealed bids will be received by the Public Works Director of Lake City, Minnesota, at the Utility Offices at 1885 S Hwy 61, Lake City, MN 55041, until 1:30 PM CDT on December 10, 2026, for Furnishing Major Materials - Electric Distribution Improvements - Feeder E4 Tie & Conversion, Underwood Egress & W3 Sectionalizing for Lake City Public Utilities, Lake City, Minnesota. At said time and place, bids will be publicly opened and read aloud.
The equipment required to be designed, manufactured, tested, and delivered is as follows:
• 15 kV Primary Power Cable
• 15 kV Padmount Switchgear (Solid Dielectric, Dead Front) and associated Box Pads
• 15 kV Padmount Switchgear (Air-Insulated, Dead Front) and associated Box Pads
• Single-Phase Padmount Distribution Transformers and associated Box Pads
• Three-Phase Padmount Distribution Transformers and associated Box Pads
The above equipment shall be in accordance with the specifications and proposed form of contract now on file in the office of Lake City Public Utilities, Lake City, Minnesota, by this reference made a part hereof, as though fully set out and incorporated herein.
Each bid shall be made out on bid forms furnished by the Engineer and shall be accompanied by either a certified check or a bid bond executed in an amount not less than ten percent (10%) of the amount of the Bid. The bid security shall be made payable to Lake City Public Utilities. The bid security must not contain any conditions either in the body or as an endorsement thereon. Such bid security shall be forfeited to Lake City Public Utilities as liquidated damages in the event the successful bidder fails or refuses to enter into a contract and post a satisfactory Performance Bond.
Material suppliers desiring a copy of the bid form and specifications for individual use may obtain them from the office of DGR Engineering, Rock Rapids, Iowa, telephone 712-472-2531, fax 712-472-2710, website www.dgr.com, email dgr@dgr.com, no deposit required.
Payment to the Supplier will be made as described in the Material Agreement.
All materials shall be delivered by the dates set in the Specifications.
Lake City Public Utilities reserves the right to defer acceptance of any bid for a period not to exceed thirty (30) days after the date bids are received and no bid may be withdrawn during this period. Lake City Public Utilities also reserves the right to reject any or all bids and enter into such contract as it shall deem to be in the best interest of Lake City Public Utilities.
Dated this 10th day of November, 2026.
LAKE CITY PUBLIC UTILITIES
LAKE CITY, MINNESOTA
By /s/ Mitchell Rigelman
Public Works Director
Published in the Lake City Graphic on November 19, 2026