Downtown work goes underground

At the weekly Highway 61 reconstruction project progress report Tuesday, Dick Swenke, Rochester Sand and Gravel’s public information coordinator, provided an update on the work that took place last week and what’s coming in the week ahead.

On the north end of the project between Central Point Road and West Vine Street last week contractors were installing storm sewer pipe and storm structures and working on roadway excavation, Swenke said.

 


Want to read the full article? Full access to lakecitygraphic.com is only $52 per year. If you live in Goodhue or Wabasha County, you'll receive the print edition in the mail each week at no additional charge. To begin, fill out the form below. Already a subscriber? Log in or request an account below.