Downtown work goes underground

At the weekly Highway 61 reconstruction project progress report Tuesday, Dick Swenke, Rochester Sand and Gravel’s public information coordinator, provided an update on the work that took place last week and what’s coming in the week ahead.

On the north end of the project between Central Point Road and West Vine Street last week contractors were installing storm sewer pipe and storm structures and working on roadway excavation, Swenke said.

 


Want to read the full article? Full access to lakecitygraphic.com is only $52 per year. Print subscriptions are $58 for Wabasha and Goodhue county residents and $80 anywhere else in the continental U.S. To begin, click here. Already a subscriber? Log in or request an account below.

User login

The Lake City Graphic

graphic@lakecitygraphic.com
Ph: 651-345-3316 (M-F 8am-4pm)
Fax: 651-345-4200
P.O. Box 469
111 South 8th Street
Lake City, MN 55041

ISSN 2994-1059 (print)  ISSN 2994-1067 (online)